Douglas Nursing Home2019-05-01T12:52:34+00:00

Project Description

Douglas Nursing Home

Cork

Project Details

Duration: 9 Months

Value: €2.2M

Project Description

Construction of a 26nr en-suite bedroom extension to an existing ‘live’ nursing home. Works also incorporated a new kitchen, extended dining room, laundry and other ancillary areas.

This €2.2m project was completed in September 2017, following a 9 month on site build process.

A Reinforced Concrete retaining wall 105m long and 2.4m high was required following excavation of 5,000t of soil and stones.

The project has been inspected and is fully compliant with the latest HIQA regs.