Project Description
ESB Ducting Works Great Island Substation
Wexford
Project Details
Duration: 1 Months
Value: €60,000
Project Description
€60k SubContract to Reach Active for laying of 780m of new 220kV Ducts just outside the existing Great Island ESB substation in Co Wexford.
Works were carried out in April 2014