Project Description
ESB/ERA Kilpaddoge
Kerry
Project Details
Duration: 12 Months
Value: €1 Million
Project Description
Laying of 5,976m of 220kV and 16,483m of 110kV Ducts for the new ESB substation along with all joint boxes C2 chambers and ancilliary works.
Works were started in Sep 2013 and were completed in Sep 2014 for circa €1m.