Client: Hilton Hotel

Duration: 17 Months

Value: €17 Million

Project Description

Another of Frank’s Projects was the shell & core for the Hilton Hotel in Kilmainham. This mixed use development came in at €17m and took approx. 18 months to construct. The building consisted of Reinforced Concrete walls and precast floor slabs combined with in-situ cantilevered balconies. A combination of curtain walling and polished stone was used to clad the building.

In total 120 bedrooms, public areas, 100 car underground car park and a leisure centre with feature swimming pool was built as part of a larger Mixed Use Development on a 2 Hectare site in Kilmainham, Dublin.

Works were completed on time, snag free and with no serious accidents or incidents